First, the early stage of construction1. Apply for the construction certificate (ordinary residences are self-installed 2. Required information (ID card, purchase contract, related...

Assembly process and detailed explanation?

First, the early stage of construction

< br >

1. Apply for the construction certificate (ordinary residences are self-installed)

< br >

2. Required information (ID card, purchase contract, related information)

< br >

3. Print a decoration notice and post it at the door of the unit to inform neighbors.

< br >

4. The construction certificate is affixed to the inside of the security door

< br >

5. Groundbreaking ceremony

< br >

6. Write a list of appliances

< br >

7. Go to the home square to see the main material inquiry

< br >

8. Determine the electrical model and main material brand

< br >

Two, hard installation construction

< br >

1. Removal (1-3 days)

< br >

In the process of demolition, garbage removal, and demolition, make an appointment to measure the broken bridge aluminum, security door, and heating.

< br >

2. To change the water and electricity (5-10 days) intelligent system needs to reserve lines in advance.

< br >

Water and electricity disclosure, circuit laying, waterway laying

< br >

Drainage transformation, heating shift and pipe change (floor heating laying)

< br >

Embedment faucet, install water purifier front

< br >

The owner accompanied the hydropower point check to calculate the quotation

< br >

In the process of hydropower transformation, choose floor drains, wall tiles, floor tiles, kickers, sun corner lines, door stones, window stones and make an appointment for installation and distribution, and make an appointment for air conditioning drilling (or installation of central air conditioning fresh air system).

< br >

3. Brickwork phase (5-10 days)

< br >

Wall building, wall tile, floor tile laying (pay attention to the level, check the joint, socket reserve point do not in the tile gap, chamfering whether there is broken porcelain)

< br >

In the process of paving, you can make an appointment to measure the door, bag mouth, custom furniture, cabinets, bathroom.

< br >

Install the broken bridge aluminum window and security door before finishing the tile shop.

< br >

4. Carpentry stage (3-5 days)

< br >

Chandelier pool, do no main lights, double eyelids, curtain boxes, etc., before the construction of the need to be embedded in the embedded magnetic track light slot prepared in advance. Buy wall paint (wall cloth, wallpaper) curtains, lamps, activity furniture.

< br >

5. Oil processing stage (5-10 days)

< br >

Wall base treatment

< br >

Grinding, scraping putty, brushing latex paint (wall cloth, wallpaper)

< br >

This process can be carried out at the same time: custom furniture, cabinet ruler, electrical size model sent to the designer. Switch panel, hardware, sewing, floor, purchase and reserve construction.

< br >

6. Beauty seam (1-2 days)

< br >

7. Heating installation (half day)

< br >

8. Kitchen ceiling (half day) If it is an ordinary smoke machine, contact the installation of check valve exhaust pipe in advance.

< br >

9. Bathroom installation (half day) If the washing machine is placed in the bathroom, be sure to put the washing machine in the bathroom door before installation.

< br >

10. Gas water heater installation

< br >

11. Cabinet installation, smoke stove installation, refrigerator into the position.

< br >

12. Door and bag opening installation (half day)

< br >

13. Clearing and cleaning (1 day) hard installation construction completed.

< br >

Three, soft assembly decoration

< br >

1. Custom furniture installation

< br >

2. Install the switch panel

< br >

3. Lamp installation

< br >

4. Air conditioning TV installation

< br >

5. Deep cleaning

< br >

6. Finishing (wall treatment, patching, gypsum line, etc.)

< br >

7. Entry of activity furniture (sofa, coffee table, bed, dining table and chair)

< br >

8. Curtain installation

< br >

9. Other accessories (decorative paintings, green plants)

< br >

Iv. Completion acceptance

< br >

1. Property acceptance

< br >

2. Owner and decoration company acceptance

< br >

3. Check for gaps

< br >

4. Finish packing


First divided into two parts, decoration process hard and then soft installation

< br \/ >

First, the hard installation part

< br \/ >

Main body demolition and renovation -- water and electricity renovation -- Woodworking -- bricker's tile -- oil painter's wall paint -- kitchen ceiling -- cabinet installation -- wooden door installation -- floor installation -- wallpaper wall fabric -- radiator installation -- switch socket installation -- hardware installation -- curtain rod installation

< br \/ >

Second, the soft installation part

< br \/ >

Easy to replace items: furniture matching - home accessories - curtains - wall hangings - carpets - bedding - lamps and decorative crafts, green plants, etc

< br \/ >

3. Home Appliances

< br \/ >

Kitchen three-piece set: smoker, stove, water heater. Refrigerator, air conditioner, TV, washing machine, microwave oven and so on.

< br \/ >

Fourth, frontier cleaning